DCT Gdańsk has completed the expansion of one of the largest rail container terminals in Europe with a capacity of 750 thousand TEU (20-foot containers). The new investment opens up development opportunities in inland markets that are landlocked and is an economically effective and "green" alternative for DCT Gdańsk customers.
The
expansion of the railway terminal was a key element of the three-year
DCT Gdańsk investment program (the so-called T2b), scheduled for
2018-2021. In addition to the expansion, the DCT entrance gates were
fully automated, where OCR (optical character recognition) cameras
were used to register trucks and containers, the number of modern STS
quayside cranes was increased to 8, the area of storage yards
was increased, and additional equipment was purchased - 5 eRTG yard
cranes
First step.
New RMG tracks and cranes
As
part of the expansion of the railway terminal, the tracks were
lengthened from 618 to 750 meters, the railway siding was widened
from 4 to 7 tracks, fully electrified RMG railway cranes were
purchased, and an OCR camera system for recording trains and
containers was launched. All this allowed to increase the throughput
capacity by rail to 750 thousand TEU.
-
We added three tracks more, so we now have seven tracks of 750 meters
long. That became too large for the RTG's, so we ordered three
rail-mounted gantry cranes, RTG's. We've managed to increase our
capacity to 750 thousand TEU for rail handling - informs Charles
Baker, general director of DCT Gdańsk.
The
gantry cranes arrived in Gdańsk in parts in July 2019 from China.
Huge pieces of new equipment were transported to the assembly site.
At the same time, work began on the development of new rails for RMG
cranes. After passing the first tests, DCT started servicing trains
on the upgraded railway siding.
An
interesting fact is that the spectacular RMG cranes are 47 meters
long, 20 meters high, 28 meters wide and are designed to work on
rails.
Wiktoria
Matlak-Paszak, project manager responsible for the infrastructural
part of the investment on behalf of DCT Gdańsk, reminds that the
construction works on the terminal started at the beginning of 2019.
What
did these works look like in detail?
-
It was the first stage of the extension of the railway siding. In
order to enable reloading operations with the RMG railway crane, it
was necessary to build a second crane beam, renovate the existing
one, and perform all accompanying works - in particular electrical
works. We are talking about high power - 15 kW - explains Wiktoria
Matlak-Paszak, civil engineer.
The
end of engineering works, sealed by an administrative decision, took
place in 2020. This investment had to be divided into stages due to
the delivery of RMG cranes.
-
When the overhead cranes arrived at the terminal, we had to make a
certain area of the yard available so that they could be
assembled, commissioned and tested for all the equipment - she says.
- After that, we started the second stage, which consisted in adding
three new tracks, extending the existing ones, reconstructing
turnouts, thanks to which we managed to connect with the second track
to DCT as part of the investment carried out by Port of Gdansk
Authority.
The project manager emphasizes that two stages of the investment were necessary. - The spacing of our previous RTG cranes is smaller than RMG cranes that run on rails - she explains.
The
second stage of the investment started at the beginning of 2021 and
ended practically at its end.
Will there be a fourth crane?
Charles
Baker admits that the terminal is in talks with suppliers about a
fourth RMG crane for the DCT rail terminal.
-
That would lift the capacity up probably to around 900,000 TEU, which
is obsoiusly in line with the growth that we are anticipating with
the development of Terminal 3 - emphasizes Baker.
-
Then we might need to find another place to put a second rail
terminal as we continue to grow into the future. Especially if the
migration from truck to train really starts to increase in the coming
years as we expect it will, as the pressure comes from the
legislavite bodies both from Poland and the European Union, and to
some extend the International Maritime Organization, pushing evermore
towards lower emmisions for cargo transportation - he says.
RMG replaced RTG. This change is "eco"
It
is also particularly important for the terminal that the RMG cranes
are electrically powered and therefore have lower emissions than the
RTG yard cranes they replace. But there are more advantages: RMGs are
larger, more efficient and faster (maximum travel speed - 150 m per
minute).
-
We do not have the final statistics for 2020 yet, but we will
probably close around 480,000 TEU at the rail terminal - Charles
Baker tells us.
DCT
spends nearly EUR 17 million on railways. Will it pay off?
The
head of the largest container terminal in the Baltic Sea reminds that
all these investments enable DCT to open more windows for rail
operators.
-
Trains from different directions and going to different places will
be able to come to us more frequently. Obviously, both us, the
shipping lines and customers like to operate these on fixed, weekly
basis. Everybody knows that those trains are programmed to and from
those destinations, so they can plan their supply chain accordingly,
because of course ship arrivals and departures are programmed on a
weekly basis as well. And we;ve been very fortunate that most of the
time during 2021 they have arrived on time, despite the problems of
congestions in other european ports – says Baker.
-
The goods will be reloaded in our railway terminal and will go by
feeders to other Baltic countries, including St. Petersburg. And vice
versa - goods unloaded from trains in Russia can flow from St.
Petersburg to Gdańsk, and we will place them on other wagons, on
other tracks, so that they can be distributed around Europe –
describes Baker.
He
points out that most of the loads that arrive by rail are destined
for Poland.
-
And this percentage is growing. Of course, there are tons of
investments in the country aimed at modernizing the railway
infrastructure, improving the tracks, improving the sidings so that
the trains can be longer. This will help us reduce the carbon dioxide
emissions associated with the cargo transport in Europe, and that is
one of our goals. We think this will also fuel rail transport. We
expect to see proportionally more containers leaving DCT on the
tracks in the coming years - emphasizes the CEO.
Open to southern neighbors
Foreign
customers will be able to generate significant cost savings by using
a shorter rail route to and from DCT Gdansk, compared to other ports
in southern or western Europe. DCT Gdańsk will work with partners
from the industry on the development of its intermodal services to
and from neighboring countries and regions with no access to the sea,
i.e. the Czech Republic, Slovakia, Western Ukraine and Belarus.
DCT
Gdańsk is directly represented on the Czech and Slovak markets,
which enables our southern neighbors to use the forwarding potential
of DCT.
-
We offer competitive delivery times and - thanks to the use of rail
connections on a large scale - we guarantee our customers lower
carbon dioxide emissions per container compared to other European
ports. The experience and scope of DCT's activities therefore give
inland customers a better, cheaper and greener alternative to
transporting goods - adds Charles Baker.
About
DCT Gdańsk
DCT
Gdańsk was launched in 2007 and has a capacity of 3 million TEU. The
terminal handles over 700 ships a year, including 100 calls of the
largest container ships in the world. In 2021, DCT Gdańsk handled
nearly 2.1 million TEU, and on April 8, 2021, it reached 15 million
TEU handled in total since its inauguration 14 years ago.
The
terminal has a significant impact on the economy; employs over 1,000
employees, of which over 50 percent lives in Gdańsk and its
vicinity. In addition, it generates over PLN 12 billion a year from
VAT, excise duty and customs duties to the state budget.
DCT
Gdańsk also undertakes activities for the benefit of local
communities, and clearly defined, measurable goals of sustainable
development are an integral part of DCT's business activities.
The
terminal is owned by PSA International (40%), Polish Development Fund
(30%) and IFM Global Infrastructure Fund advised by IFM Investors
(30%). PSA International is a leading global port group and a trusted
partner for cargo companies around the world. With flagship
operations in Singapore and Antwerp, PSA's global network includes
more than 50 locations in 26 countries around the world. The Polish
Development Fund Group (Polski Fundusz Rozwoju, PFR) is a group of
financial institutions offering instruments for the development of
enterprises, local governments and private individuals, investing in
sustainable social and economic development. IFM Investors is a
global institutional fund management company worth $ 118 billion (as
of March 31, 2021).