PORR won the tender for the construction of the hydrotechnical part of the offshore installation terminal in Świnoujście, announced by the Szczecin and Świnoujście Seaports Authority. The works are scheduled to last until mid-2025.
PORR will be responsible for
expanding quays no. 1 and 2 (they will be extended to 250 meters
each) and deepening the water area to 10.5 meters. A sheet piling
will also be built for the future quay no. 3, and dredging works are
to deepen this part to 12.5 meters. Part of the water area between
the planned wall and the current quay no. 3 will be landlocked. The
contractor will also have to obtain appropriate use permits for each
part of the investment. Ultimately, two 250-meter quays will be
built, capable of servicing installation ships.
At the same time,
work on the land part will be carried out by Budimex. On the sites it
develops, it will be possible to pre-assemble wind turbine elements
with dimensions exceeding 100 meters in height and weighing 1,000
tons. The land part of the works on the Baltic Power terminal in
Świnoujście is to be completed in December 2024.
PORR is a
Polish company experienced in complex hydrotechnical works. The offer
it submitted in the tender amounted to PLN 170,623,352.94 and was the
lowest of the total of nine submitted to the Szczecin and Świnoujście
Seaports Authority, while there was a difference of over PLN 110
million between PORR's offer and the highest one submitted in the
tender.
The consortium of Gap Insaat Yatirim Ve Diş Ticare and
Fabe Polska (PLN 176.81 million), the consortium of NDI and NDI SOPOT
(PLN 183.69 million), Budimex (PLN 187.38 million), the consortium of
Roverpol and Rover Maritime (PLN 228.78 million), Doraco (PLN 236.87
million), Erbud (PLN 238.55 million), Strabag (PLN 277.37 million)
and China Harbor Engineering Company (PLN 286.86 million) also
submitted offers in the tender.