PGE and Ørsted launched a tendering procedure for
the construction of onshore infrastructure necessary for power
output from both wind farm phases of the Baltica offshore wind
farm, i.e. Baltica 2 and Baltica 3. According to the plans, the
tender should be resolved by the end of this year.
-
Preparation for construction of the onshore part of the Baltica
offshore wind farm infrastructure and its implementation is a
several-year process that runs parallel to the preparatory work at
sea. The year 2022 will be very intensive for us in terms of
tendering procedures for power output, and the first onshore
construction works are planned to commence in the fourth quarter of
2023 - said Wojciech Dąbrowski, President of the Management Board of
PGE Polska Grupa Energetyczna.
- We are proceeding
according to the set schedule, conducting several parallel processes,
both with respect to tendering procedures, such as the one for the
construction of the onshore part of the infrastructure, and with
respect to the obtaining of permits and financial closing of the
project. Our common ambition is that clean and affordable energy from
Baltica offshore wind farm will flow into Polish homes and businesses
as planned in 2026 - adds Søren Westergaard Jensen, director of the
Baltica offshore wind farm project on behalf of Ørsted Polska and
managing director of the offshore area of the company.
The
tender procedure was announced and will be carried out by PGE
Baltica, which executes the Offshore Programme of the PGE Group, and
the agreement with the selected general contractor will be signed
jointly by PGE Baltica and Ørsted, which form a joint venture
constructing the offshore wind farm Baltica.
The onshore
connection infrastructure for the Baltica OWF will be constructed in
the vicinity of the village of Osieki Lęborskie, commune of
Choczewo, poviat of Wejherowo, Pomerania. Two adjacent onshore
substations - one for Baltica 3 and the other for Baltica 2 - will be
built with export cable lines leading to them in the onshore area.
The task of the successful general contractor will be to carry out
the contract in the "design and build" mode.
The
task includes not only the construction of transformer stations and
export cable lines in the land area, but also, among others, access
and internal roads, water and sewage network for the needs of the
station, its lighting and fencing. The tender schedule provides for
its award by the end of 2022. The first construction works related to
the onshore station are expected to start in the fourth quarter of
2023.
According to the schedule for the first stage of
the project, i.e. Baltica 3 with a capacity of up to 1,045.5 MW, the
introduction of first energy to the grid is planned for 2026. The
next stage, Baltica 2 with a capacity of up to 1,497 MW, is expected
to begin production by 2027. These investments will help accelerate
Poland's energy transition. Both Baltica offshore wind farm stages
have obtained location decisions (PSzW), environmental decisions for
the offshore part, transmission grid connection agreements with the
operator and have been granted the right to a Contract for Difference
(CfD). In 2022, the project partners expect to receive the
environmental decision for the onshore transmission portion, and will
begin work on obtaining construction permits. This is the last permit
required before a final investment decision is made.
Detailed
information about the order at Tenders Electronic Daily.