Two
maneuvering and storage yards, i.e. over 17 hectares for the storage
of containers and wind farm elements, will be ready half a year ahead
of schedule. 85,000 cubic meters of concrete were needed to complete
the Logistics Center investment in the Port of Gdynia.
Storage
and maneuvering yards were built on the premises of the Logistics
Center at ul. Logistyczna in Gdynia. The general contractor is the
Sopot-based company NDI, which has kept the pace of work from the
very beginning.
- The current stage of work advancement is
over 90 percent. In November, we completed the concrete pavement
laying works. Thanks to the full commitment of the team and
subcontractors, over 185,000 m2 of surface were completed within six
and a half months - says Przemysław Młynarczyk, construction
manager at NDI. - According to the contract, the completion date of
the investment was planned for the end of June 2022, so we were ahead
of it by about half a year.
And what's next?
The fence
around square no. 2 is currently being built (it is already built on
square no. 1). The assembly of cooling platforms and a fire-fighting
tank with a pumping station are in progress. The plans also include
minor paving works, soil humusification and construction of green
areas, as well as the assembly of control cabinets for cooling
platforms and the completion of the assembly of the platforms.
-
They will be made as soon as the weather permits. But now the squares
are ready to be put into use - emphasizes Przemysław
Młynarczyk.
The squares are 45 centimeters thick and have a
load capacity of 20 tons per square meter. About 55 thousand m3 of
pavement concrete were used for their construction and about 30
thousand m3 of concrete were needed for the main foundation. The
surface was arranged in a single layer, made of fiber-reinforced
concrete. In addition, concrete slabs were dowelled in all
directions. Such a quick implementation of this investment was
possible thanks to the combination of various paving technologies and
the setting of a concrete mixing plant on the construction site. The
works were carried out 24 hours a day.
A chance for
development
The investment of the Port of Gdynia also included
the execution of a linear drainage system as well as the
reconstruction and construction of underground and overground
utilities, i.e. the construction of a rainwater sewage system,
sanitary sewage system, water supply system, the so-called hydrant
with a tank and fire water pumping station.
- Cooperation of
the Port of Gdynia Authority with the construction corporation NDI
S.A. can be an example of how to carry out such projects in an
exemplary manner. From the very beginning, the contractor showed
great commitment to the project implementation. For us, the yards and
infrastructure in the western part of our port open up new
possibilities for servicing various cargo groups - starting with
those that have been present in our port for many years, as well as
completely new, such as elements of offshore wind farms. These
activities are the key to the competitiveness of the port and enable
the continued high level of functioning of the Port of Gdynia - says
Jacek Sadaj, President of the Port of Gdynia Authority.
The
value of the investment is over PLN 70.7 million net. Thanks to the
new yards, the Port of Gdynia has a chance for development. Already
today, the city is part of the trans-European transport network,
which is why the intermodal connections that will be implemented in
this part of the port are so important.