The company has signed a reservation contract with Cadeler of Denmark for the transport and installation of some 70 turbines for the Baltic Power offshore wind farm – a joint project of PKN ORLEN and Northland Power Inc. In the next steps, the company will select contractors to supply the turbines, foundations, internal and export cables, to construct offshore and onshore substations, and to provide farm maintenance services. The project, planned to be executed between 2024 and 2026, will involve the construction of a wind farm with a total generating capacity of up to 1.2 GW.
“Fullfilment of the contract is an important step in our
procurement strategy, which assumes that all critical components and
services necessary to complete the project on schedule should be secured
by the end of this year. The vessel we have booked is one of
approximately fifteen in the world capable of installing the latest
generation of turbines,” emphasizes Jarosław Broda, Member of the Baltic Power Management Board.
Cadeler
specialises in the installation of offshore turbines. Since 2012, it
has installed nearly 400 offshore wind turbines and more than 500
foundations, which together generate energy for more than 5.5 million
European households. The signed reservation agreement guarantees the
availability of a specialized vessel for turbine installation during the
construction phase. The final agreement will be signed once Baltic
Power has made a final investment decision.
In June
this year, Baltic Power completed a geotechnical survey, as the first
wind farm developer in the Polish part of the Baltic Sea. The
measurements were carried out over the farm’s site, with an area of more
than 130 km2, and along the over 30 km long
power evacuation route. A team of several hundred surveyors, technicians
and operators performed thousands of measurements and soundings. The
vessels involved in the campaign worked for more than 20 thousand hours,
during which several thousand metres of specialist boreholes were
drilled at planned locations of the foundations of various
infrastructure components. Depending on the location, the drillings were
made up to a target depth of several dozen metres.
Thanks to the effective transfer of knowledge and hard work involving almost 90 experts, Baltic Power has become one of the fastest paced projects on the Baltic Sea. The construction of a wind farm with a capacity of up to 1.2 GW is scheduled for 2024–2026. During that time, about 70 wind turbines with a minimum capacity of 14 MW will be erected in the sea, ultimately supplying clean energy even to one million households.