MPP,
a one-of-a-kind specialized pontoon that was constructed for the
construction of an underwater tunnel connecting Germany and Denmark,
has sailed away from the CRIST shipyard in Gdynia. The vessel is
being towed to Klaipėda, where it will spend some time before
traveling to Denmark. There she will face sea trials.
MPP is the newest addition to the portfolio of the CRIST shipyard in Gdynia. It is a steel pontoon, designed and built for a specific purpose - to lay gravel on the seabed, on which elements of an undersea tunnel will be placed. The tunnel will shorten the route between Germany and the Danish island of Loland. The vessel is designed strictly for this specific purpose, which influenced, among other things, its dimensions. The MPP hull is 130 meters long, and the entire pontoon including the transmission belts is 149 meters long. At the same time, it is distinguished by a very low draft. The two chambers on board can accommodate 14,000 tons of gravel, which will then - thanks to a special laying device - be precisely placed on the seabed. The construction of the vessel was commissioned by the consortium Femern Link Contractors, responsible for the construction of the 18-kilometer Femern Link tunnel, which will stretch from Puttgarten in Germany to Rødbyhavn in Denmark. The CRIST shipyard started work on the MPP in 2021, and in the first half of October 2023, it officially handed over the pontoon to the shipowner. The structure sailed from Gdynia on October 30 in the morning. On this complex project, the CRIST shipyard cooperated with, among others, with the Polish design office StoGda.
MPP does not have its own engines -
ultimately it is to operate on only an 18-kilometer stretch of sea,
so installing powerful power engines would be a waste of space.
Therefore, the 130-meter-long structure was pushed off the Dokowe
Quay at the CRIST shipyard in Gdynia with the help of Fairplay
tugboats. One of them, Fairplay-85, was pushing the MPP from the
stern, two were guarding the pontoon from the sides, and Fairplay-35
was pulling it in tow. And it was the latter who was responsible for
towing the unique construction to Klaipėda. There, at one of the
quays, the MPP will be waiting for sea trials, which will take place
in Denmark. Part of the crew has already gone to Lithuania and will
continue to familiarize themselves with the procedures on the vessel
in order to be ready to start the actual work at the Femernlink
construction site.
The entire operation to tow MPP to
Klaipėda began this morning around 8 a.m. Fairplay-35 and MPP safely
passed through the Port of Gdynia gate about forty minutes later. The
process was observed by, among others, chief designer of a unique
pontoon.
However, the farewell of MPP does
not end the adventure of the CRIST shipyard with vessels for the
construction of a tunnel under the Fehmarn Belt. Work is underway in
the shipyard dock on another complex project with construction number
NB 100. It will be used for the transport and installation of
prefabricated tunnel elements.
When completed, Femernlink will be
the longest road-rail tunnel in the world, the longest underwater
road tunnel in the world, the deepest road-rail tunnel in the world
and the second deepest buried concrete tunnel in the world.